Topographic survey for the basic design phase of the project: Construction of the road connecting Route 23B to Chu Phan Port, Mê Linh District.

Scope of Work:

  1. Conduct a 1/1000 scale topographic survey of the traffic alignment for Route Option 1, covering a length of 9.6 km.
  2. Establish a control network and perform a 1/1000 scale topographic survey of the traffic alignment, including intersections and bridge layouts along a 6.2 km section (from km 3+600 to the left dyke of the Red River).
  3. Carry out longitudinal and cross-sectional surveys over a 6.2 km stretch.
  4. Investigate underground and aboveground technical infrastructure, as well as survey material disposal sites and material sources for the project